11,883m evacuation platform(emergency walkway made of composite material) for Wuhan Rail Transit Line 19

Aug 03, 2023
Wuhan Rail Transit Line 19 is a city wide express line in the rail transit network of Wuhan. Together with Line 20, it will build an airport complex hub, forming a fast and direct connection between the high-tech zone, high-speed railway Wuhan railway station and Tianhe hub.

Wuhan Rail Transit Line 19 focuses on serving the central city axis of East Lake High tech Optical Valley, strengthening the connection with Wuhan Huanghua Inter-city rail, high-speed railway Wuhan railway station, Tianhe Hub and other external transportation hubs, and supporting the development of Huashan and East Lake High tech Zone.
The total length of Wuhan Rail Transit Line 19 is about 23.3km (an increase of about 2.1km), with 7 stations (an increase of 1 station), all of which are underground stations. The maximum station spacing is 6.7km, from Huashanhe Station to Guanggu 5th Road station, and the minimum station spacing is 1.0km, from Guanggu 5th Road station to High tech Second Road Station, with an average station spacing of about 3.8km. The Minimum railway curve radius of the line is 500m, and the maximum line gradient is 24 ‰. This line has a connecting line between Gaoxin Second Road Station and Rail Transit Line 13.

The total planned construction period of Wuhan Rail Transit Line 19 is 420 days. Start date: July 15, 2022, completion date: September 7, 2023.

In 2023, Anyang Railway Equipment Co., Ltd(AT) supplied 11,883m evacuation platform(emergency walkway made of composite material) for Wuhan Rail Transit Line 19, in accordance with the technical specification of T/CECS 10180-2022 Metro Tunnel Evacuation Platform.
Evacuation platform(emergency walkway made of composite material)  Manufacturer - Anyang Railway Equipment